Construction Update on Laguna & Glade April 2024
20 April 2024
We're thrilled to update you on the ongoing development of Laguna and Glade, Stage 2 at Sanctuary Wentworth Point and share the construction progress and milestones achieved in the last following months.
We are excited to provide you with the latest construction update for Stage 2, Laguna and Glade at Sanctuary by Sekisui House’s waterside community.
Construction of Laguna (Building N) is currently up to Level 11, whilst internal services rough-in and wall framing is underway to Level 6. Level 1 has commenced wall sheeting with internal tiling also set to commence.
On Glade (Building O), Level 6 is currently being poured with the remainder of the structure expected to be complete in the coming week. High level services rough-in and internal framing has commenced on Level 1.