Melrose Park Village March Project Update

25 March 2024
Construction Update March

We’re thrilled to share some construction milestones we have reached this year at Melrose Park Village.

It has been a busy start to the year and the podium level is now fully complete, marking a pivotal moment in the journey of Melrose Park Village, our fourth stage in the northern precinct. Buildings 4, 5 and 6 are also making impressive progress, with scaffolding erected up to level 4. We're maintaining daily concrete pours, with a new floor constructed every three weeks to keep things moving along.

In even more exciting news, we are fast-tracking two prototype units, giving buyers an early sneak peek at their future apartment finishes.

 